Land Dedication Service
Ground Breaking Ceremony
Land Developement
Building Project
home
Pictures from Land Dedication Service, June 1, 2008
Gathering at original building.
Dedication Service
Children are the future of our church.
Pictures from Ground Breaking Ceremony, April 4, 2009
Sara and Ellen try out the "BIG" equipment.
Pictures from Land Developement
Machinery stripping topsoil
Posts marking grades on site work .
Voluteers put up silt fence.
Digging culverts.
Volunteers raking and seeding grass.
Volunteers picking rocks.
Even the kids help.
Entrance to new building lot.
Grass growing at retention Pond.
Sand mound in place.
Curbing around driveway and parking lot.
Pictures from Landscaping and buildi ng Project
Trees planted on site. 10-29-09
Building pad. 11-06-09
Backhoe dig footers. 11-06-09
Footers ready for cement. 11-06-09
Footers formed. 11-09-09
Pouring footers. 11-09-09
Footers done. 11-09-09
Drilling the well. 11-09-09
Block Wall 11-11-09
Parking lot lights are installed. 11-16-09
Electrical Conduit goes in. 11-18-09
Trucks lined up. 11-22-09
Unload steel for building. 11-22-09
Backfill around foundation. 11-22-09
Steel for building. Just like a giant erector set. 11-24-09
Building forms for entrances. 11-28-09
Steel building goes together. 12-07-09
Pipes go in for the plumbing. 12-07-09
Windows and doors installed. 12-10-09
Starting the windows and siding. 12-10-09
View of parking lots. 12-11-09
Poured walks at the entrances . 12-11-09
View of the multi-purpose phase. 12-11-09
One end with siding on. 12-13-09
Plumbing in the floor. 12-14-09
Electrically work on outside panel. 12-15-09
Roof being installed. 12-16-09
Siding and insulation finished. 12-17-09
Building the entryway. 12-18-09
Hanging temporary lights. 12-18-09
Stone on floor. 12-21-09
Plastic and foam on floor. 12-23-09
Foam on floor. 12-23-09
Cement trucks line up to fill hydralic pump. 12-28-09
Concrete pumped into the building. 12-28-09
Concrete floor. 12-28-09
Concrete floor half-way finished. 12-28-09
Concrete finished and curing. 12-28-09
Lumber delivered. 01-04-10
Measuring metal studs for firewall. 01-04-10
Building firewall between sanctuary and S. S. rooms. 1-5-10
Begining of outside entrance. 1-11-10
Drywall begins to go up. 1-11-10
View into classrooms and sanctuary from gym. 1-11-10
Plywood goes up on gym walls. 1-13-10
Drywall in sanctuary. 1-14-10
Building walls for restrooms and S. S. rooms. 1-14-10
Electrical wiring starts. 1-17-10
Plumbing begins for restrooms. 1-19-10
Plywood end wall of gym. 1-19-10
Upper deck of Sunday School rooms begins. 1-20-10
Putting up duct before walls are built. 1-22-10
Future stairs. 1-22-10
Drywall delivery to second floor. 1-25-10
!st time we turn on parking lot lights. 1-27-10
Install electrical panel. 1-28-10
Sanctuary spackeld. 1-31-10
Installing stairway. 2-2-10
Installing drop ceiling for 2nd floor classrooms. 2-4-10
LIghting hung in gym. 2-4-10
Studs for upstairs Sunday School rooms. 2-7-10
Painting begins in restrooms. 2-8-10
Drywall and insulation for 2nd floor classrooms. 2-8-10
Installing front doors. 2-11-10
Youth among many other volunteers paint everywhere.
Putting together duct for sanctuary. 2-18-10